Pilchuck Creek Hydroelectric Project

Squamish, BC

Statistics:

bullet

Turbine: single nozzle Pelton

bullet

Generator: 100kW Westinghouse @ 1200 RPM

bullet

Rated head: 218m

bullet

Rated flow: 0.050m3/sec

bullet

Commissioned: 2021

The project is owned and built by Queen of Peace Monastery. It generates enough clean energy for their property. Under BC Hydro's Net Metering program, BC Hydro will pay the nuns when the nuns use less power than their project produces.

   

Installed Pelton Turbine-Generator

Installed Pelton Turbine-Generator

Installed Switchgear and Control Panel

Installed Switchgear and Control Panel

 

 

Back to Projects page.

  • Back to Top

  • horizontal rule

    Dependable Turbines Ltd. 17930 Roan Place Surrey, B. C. Canada V3S 5K1
    Phone (604) 576-3175 Fax (604) 576-3183 Email: sales@dtlhydro.com

     

    Copyright 2021 Dependable Turbines Ltd.  All rights reserved.