Gosan Hydro

South Korea

Statistics:

bullet

Turbine: One 600mm Vertical Francis

bullet

Generator: One 600kW Induction Generator @ 900 RPM

bullet

Commissioned: January 2010

The purpose of this project is to contribute to the international effort to prevent global warming as part of the government policy which promotes the development of renewable energy technology in Republic of Korea.

The plant is located in front of the settling pond in the Gosan Water Purification plant.  Water is drawn from Woonmoon Dam through a water supply pipeline.  The turbine was designed by DTL and manufactured in Korea.  The generated power is being fed to the electric grid.

 

   

Powerhouse

Turbine and inlet valve

   

Control panel

Hydraulic power unit

   

Back to Projects page.